New Builds NEW BUILD 042

Week 50

Click on any of the images below to view in more detail.

Painting continues in the engine room 

The fish room rear bulkhead with insulation fitted and framing being built 

The fish room front bulkhead with partitioning under construction 

An extractor fan has been fitted in the galley 

Worktops have now been fitted in the galley 

A small net pond has been built on the starboard side of the upper deck 

A matching net pond on the port side 

Installation of the electrics is progressing in the wheelhouse 

A small capstan winch has been fitted each side of the shelter deck 

The hydraulic pipework for the main winches has been completed