New Builds NEW BUILD 042

Week 45

Click on any of the images below to view in more detail.

Painting pipework in the deck house 

The ceiling in the fish room has been lined with plywood panels 

Another view of the ceiling in the fish room 

Preparations for spraying fibre glass onto the fish room ceiling 

Cabling for lights is being installed in the galley 

Cabling for lights is also being installed in the mess 

Fitting of the hand rails on the upper deck is now almost complete 

The rails round the upper deck seen from the bow 

Progress in the wheelhouse; looking aft 

Progress in the wheelhouse; looking for'ard