New Builds New Build 040

Week 5

Click on any of the images below to view in more detail.

The plating of the accommodation section is now complete 

Bogies have been attached to move the accommodation section out into the yard 

A tow coupling has also been fitted to the accommodation section 

The engine room has been moved out into the yard 

More work has been done on the keeel