Building wall framing in the accommodation access stairway
Finishing off the handrails on the upper deck
Cable trays are being fitted in the engine room
The main engine and gearbox are now in place
The port auxiliary engine is now in the engine room
The two starboard auxiliary engine s have also been lifted into the engine room
Paneling of the deck house is now well under way
Electrical cables are now being run through the deck house
The seating in the mess area is taking shape
Decking and its supports are being fitted on parts of the upper deck, behind the wheelhouse
The flooring has now all been laid in the wheelhouse
Framing of the wheelhouse roof now looks to be complete
Electrical cables are being run into the wheelhouse
Paneling of the wheelhouse walls is progressing well