New Builds New Build 039

Week 47

Click on any of the images below to view in more detail.

Floor units in the Galley are now complete 

The wall units in the galley are also complete 

Equipment waiting to go into the galley 

The fish room floor is about to have the concrete laid 

The cooling pipes have been fitted to the rear bulkhead in the fish room 

The cooling coils have been fitted to the fish room ceiling 

The mast has now been fitted and equipment installed upon it 

Pulley blocks and floodlights are now fitted to the gantry